Regulations of work execution in the protection zones of transmission network

Regulations of work execution refer to 110/330 kV overhead powerlines and protection zones of 110 kV and 330 kV cable powerlines. Regulations of work execution are reviewed after coordinating the relevant project with Augstsprieguma tīkls AS (AST) within the provided order.

The following conditions of work execution must be observed – two weeks before the planned commencing of the works:

  • an application must be submitted to AST, which includes information on the character of the works, the necessity of disconnecting the electrical installation, full name of the particular 110/330 kV electrical installation (line No., support No.), the time of work execution and the responsible persons. The application must be prepared on a company form and must be signed by the company manager;
  • work execution project must be submitted – developed taking into consideration the Construction Regulations of Electrical Installations in accordance with the Protection Zone Law, the methodology of identifying the Protection Zones and other regulations in force.

The work execution project must contain the following information:

  • the relevant persons (work managers, the persons responsible for freight lifting, power safety, signed copies of the certificates of these relevant persons) and their phone numbers;
  • the planned labour protection at the site, and labour protection measures regarding the 110/330 kV electrical installation;
  • mechanisms, freight lifting devices must be provided along their maximum manufactured/produced height and working height;
  • a description on the execution of works: the order of work implementation, organisational measures, assembly and disassembly of machinery (cranes, hoists etc.), movement of machinery and persons in the protection zone of the electrical installation or near it, which is related to observing safe distances regarding the power installation, the relocation of construction materials, structures;
  • the responsibility, guarantees and the mechanism for compensating the renovation costs of electrical installation of the Contractor, if losses have been incurred while implementing the works;
  • drawings that provide the location of machinery and structures in respect to the nearest cable or construction element of the electrical installation with adjustments in centimetres. The location must be provided in vertical and horizontal section in the vicinity of the electrical installation. The maximum heights of the machinery must be provided in the drawing, as well as the heights of the electrical installation (cables, structures) at the site from the ground level. Additional information required can be received in the Line Service division of Augstsprieguma tīkls AS.

The application and the work execution project must be submitted for registration at the Document Management Department of AST. Work execution project is only coordinated after all of the above mentioned requirements are met.

The coordination text must include information about additional safety measures, instructions (the person providing the instructions, phone), the responsibility of the contractor’s responsible work managers and work executors, the provision of executive documentation after the works are completed (if necessary). In case of necessity a supervisor is appointed.

Accuracy of the executive project in terms of the electric safety taking into consideration the information submitted by the contractor is a responsibility of the supervisor of the Line Service Section of the Augstsprieguma tikls AS or his/her substitute, head of the Line Service or his deputy.

Notifications

23.08.2026. on 03:35 station No. 13 "Sigulda" is out of order. Affected area: Sigulda, Siguldas novads. More info: Map of transmission system network or Map of distribution system network.

23.08.2026. on 03:35 station No. 276 "Ieriķi" is out of order. Affected area: Ieriķi, Cēsu novads, Siguldas novads. More info: Map of transmission system network or Map of distribution system network.

23.08.2026. on 02:53 station No. 89 "Madona" is out of order. Affected area: Madona, Madonas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:46 station No. 232 "Preiļi" is out of order. Affected area: Preiļi, Preiļu novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:45 station No. 88 "Barkava" is out of order. Affected area: Lubāna, Madonas novads, Varakļānu novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:45 station No. 95 "Viļāni" is out of order. Affected area: Viļāni, Varakļāni, Rēzeknes novads, Varakļānu novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:25 station No. 2A "Ķegums" is out of order. Affected area: Ogres novads, Ķekavas novads . More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:25 station No. 11 "Ogre" is out of order. Affected area: Ogre, Ogres novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:25 station No. 14 "Lielvārde" is out of order. Affected area: Ogres novads, Aizkraukles novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:25 station No. 42 "Stelpe" is out of order. Affected area: Bauskas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:25 station No. 2 "Ķegums" is out of order. Affected area: Ogres novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 23:25 station No. 45 "Iecava" is out of order. Affected area: Iecava, Iecavas novads, Bauskas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 22:51 station No. 132 "Daugavgrīva" is out of order. Affected area: Rīga (Rītabuļļi). More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 22:49 station No. 10 "Salaspils" is out of order. Affected area: Salaspils, Salaspils novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 21:58 station No. 20 "Krustpils" is out of order. Affected area: Jēkabpils (Krustpils), Jēkabpils novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 21:58 station No. 24 "Tēraudlietuve" is out of order. Affected area: Jēkabpils (Krustpils), Jēkabpils novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 21:41 station No. 41 "Olaine" is out of order. Affected area: Jelgavas novads, Olaine, Jaunolaine, Olaines novads, Ķekavas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 21:18 station No. 26 "Aiviekste" is out of order. Affected area: Jēkabpils novads, Madonas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 20:48 station No. 28 "Jēkabpils" is out of order. Affected area: Jēkabpils, Sala, Jēkabpils novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 20:15 station No. 44 "Dobele" is out of order. Affected area: Dobele, Dobeles novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 19:41 station No. 25 "Birži" is out of order. Affected area: Jēkabpils novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 19:36 station No. 22 "Nereta" is out of order. Affected area: Nereta, Aizkraukles novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 19:36 station No. 27 "Viesīte" is out of order. Affected area: Viesīte, Jēkabpils novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 18:30 station No. 39 "Ilūkste" is out of order. Affected area: Ilūkste, Subate, Augšdaugavas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 18:23 station No. 169 "Ugāle" is out of order. Affected area: Ugāle, Ventspils novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 18:18 station No. 98 "Dagda" is out of order. Affected area: Dagda, Krāslavas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 18:17 station No. 33 "Krāslava" is out of order. Affected area: Krāslava, Krāslavas novads, Preiļu novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 18:17 station No. 93 "Ludza" is out of order. Affected area: Ludza, Ludzas novads. More info: Map of transmission system network or Map of distribution system network.

22.08.2026. on 18:17 station No. 99 "Zilupe" is out of order. Affected area: Zilupe, Ludzas novads. More info: Map of transmission system network or Map of distribution system network.