Modernization and development of transmission network

Latvian electricity transmission system operator Augstsprieguma tīkls AS is responsible for the safety of electricity supply and modernization and development of transmission network. Major development projects are shown on the map.

Key development projects and their costs

Project

Year of implementation

Total costs

EU co-financing

Congestion income

Technical parameters

Kurzeme Ring (Ventspils – Tume – Imanta)

2019

127 MEUR

55 MEUR

11 MEUR

Length – 206.48 km
Line Riga CHP-2 – Riga HPP

2020

15 MEUR

7 MEUR

7 MEUR

Length – 12.89 km
Estonia – Latvia 3rd interconnection

2021

79 MEUR

51 MEUR

38 MEUR

Length in Latvia – 176.22 km
Line Valmiera – Tartu

2023

15 MEUR

11 MEUR

4 MEUR

Length in Latvia – 48.42 km
Line Valmiera – Tsirguliina

2024

14 MEUR

10.5 MEUR

3.5 MEUR

Length in Latvia – 48.47 km
Synchronous condensers

2025

114 MEUR

85 MEUR

 

Three synchronous condensers, reactive power per unit – 100 MVA
Electricity storage battery systems (BESS)

2025

77 MEUR

~80%

 

Capacity – 80 MW

Energy capacity – 160 MWh

Line Ventspils – Brocēni – Varduva

2032

~100 MEUR

Planned 50%

 

Length in Latvia to be specified in the environmental impact assessment 
Estonia – Latvia 4th interconnection

2035+

~405 MEUR

Planned 50%

 

Length in Latvia to be specified in the environmental impact assessment 

The power transmission network is developed according to the Latvian power transmission System Development Plan and the European Ten Year Network Development Plan. Those Latvian projects are included in the European Ten Year Network Development Plan that are strategically important not only nationally, but for the Baltic Sea Region in general, and inclusion in the European Ten Year Network Development Plan is one of the preconditions for the projects to be able to apply for European co-funding.To provide for safe operation of the Latvian electricity system, effective functioning of the electricity market and to prevent ageing of equipment, Augstsprieguma tīkls AS is reconstructing and modernising the high voltage substations and the points of electricity distribution. Considering the trends in the development of electricity systems in Latvia and neighbouring countries, Augstsprieguma tīkls AS is assessing and deciding on the need to develop interconnections of the Latvian power transmission system and to strengthen and modernise the internal network.

The above development projects may be funded from various sources:

  • One of the principal sources of funding is the power transmission tariff approved by the Public Utilities Commission, a certain portion of which is intended for development projects;
  • It is possible to attract European co-funding from the CEF (Connection Europe Facility)  for strategically and internationally important power transmission network development projects;
  • Development projects that increase the cross-border transmission power and eliminate bottlenecks in the power transmission network may be funded from the congestion management revenue of the transmission system operator, which is generated from the difference in electricity prices in different trading regions due to insufficient cross-border transmission power.
Pārvades tīkla attīstības projekti
The Kurzeme Ring is a project of energy infrastructure envisaging the construction of a 330 kV overhead high voltage power transmission line in the western part of Latvia to eliminate the impossibilit...
Estonia – Latvia third power transmission network interconnection is an important future infrastructure project for the Baltic Sea region that will increase the security of power supply in the region,...
The project 330 kV Power Transmission Line Riga CHP-2 - Riga HPP is included in the Latvian power transmission system development plan as well as the European ENTSO-E ten year development plan. The&nb...
The project includes the reconstruction of existing 330kV interconnections between Estonia and Latvia Valmiera (LV) – Tartu (EE) and Valmiera (LV) – Tsirgulina (EE), which are combined into one activi...
In 2024, "Augstsprieguma tīkls", based on the conducted studies on the need to strengthen the transmission grid in Kurzeme, has begun work on the project "Construction of the 330 kV power transmission...
The Battery Energy Storage System (BESS) is one of the most important projects in the synchronisation of Baltic power grids with the continental Europe electricity system in order to ensure operat...
Building a synchronous condenser station will help to maintain inertia and stability within the transmission network. This will be particularly important after the synchronisation of the Baltic States...